TO : Anja Wiederhausen

Auto Wash Inc

Dayton Ohio

CC : Stan West

Westan Builders , Inc

Re : Inspection Report

Summary

An inspection of the construction work and equipment at the Boulder site , one of the three sites in the turnkey project for High Gear Car and Truck Rentals (HGTCR ) was performed last May 9 . The proposed provisions in the contract drawn were not implemented by Westan Builders , Inc . such as the measurement for the cable troughs and sanding of newly constructed concrete edges . Most of the equipment delivered by

Auto Wash , Inc . was found satisfactory except for a few items that are missing such as cables and hook-up seals . Some of these items have been probably tampered with or stolen , the cause of which should be sought out immediately

Details from inspection of construction work

Construction debris have been left scattered around concrete shell including two piles of gravel and soil , shards of wood that were used for the concrete pours , several strips of metal , and lunch bags and drink containers of the construction workers

About 20 of the new concrete edges remain rough and have not been smoothed or sanded down

Cable and wire troughs running between the locations of the entry control box and computer control unit do not meet required depth and width stipulated in the contract . Troughs should be 1 5 /8 inches in depth and 2 inches wide . Actual troughs measure a depth of ranging...